Pavilion Project Diary
Countdown to 2nd August (Presidents Day)...
To see (and remember) the old pavilion click here.
 Day One - Thursday 18th June: Work Commences
The Pavilion Starts to be demolished! .... See all photos from Day 1 here
 
Day Two - Thursday 19th June: Demolition Complete!
To Quote Nige Hill .."Now we are in this for the long term". All Day 2 Photos are here
 
Day Six - Tuesday June 23rd: Footings Dug
All Day 6 Photos are here
 
Day Seven - Wednesday June 24th: Footings Down
"Bring on the brickwork!" .... All Day 7 Photos are here
 
Day Nine - Friday June 26th: Taking Shape..!
All Day 9 Photos are here
 
Day Thirteen - Tuesday June 30th: Slab Level...
All Day 13 Photos are here
 
Day Sixteen - Friday 3rd July: Outside Walls!
All Day 16 Photos are here
 
Day Twenty-Two - Thursday 9th July: Base for internal walls
All Day 22 Photos are here
 
Day Twenty-Three - Friday 10th July: Getting there....
All Day 23 Photos are here
 
Day Twenty-Six - Monday 13th July: A Window!
All Day 26 Photos are here
 
Day Twenty-Eight - Wednesday 15th July: A Roof!
All Day 28 Photos are here
 
Day Thirty Three - Wednesday 22nd July: More Progress..
All Day 33 Photos are here
 
Day Thirty Five - Friday 24th July: Getting There...
All Day 35 Photos are here
 
Day Thirty Nine - Tuesday 28th July:
All Day 39 Photos are here